The basic approach is that we want to start with a test bed
(see section 5). This setup will be built during the
summer of 1997. Data taking will start in the late summer.
If the test bed is a success, we will try to find a handful (10...30)
ISP's who are interested in having a test-box installed at their sites. These
boxes will be used to test of the order of 100 connections, where the
number of 100 is set by the data volume that can be handled without
major investments in storage devices. This setup will start running early
1998. Several ISP's, both from the RIPE community and from those participating
in the TERENA TF-ETM working group [8], have shown interest
in hosting our test-boxes.
After this setup has proven to be a success, we will develop a plan to
include more ISP's and connections.
A more detailed plan of deadlines and milestones can be found in
table 1.